Wednesday, May 23, 2012

Week of 5/14 - 5/18 2012

 Moving along with finishing touches to the Sports Park!

One synthetic turf field 95% complete!
Goal post upright install
 
Adding sand and crumb rubber infill to synthetic turf field

Ball Diamond Pavilion entry way

Ticket booth for Sports Fields
 
New spray rig!
 
Miracle Field concession/restroom building

Rubber surface installation on Miracle Field


Monday, May 14, 2012

Synthetic Turf Install Continued....

Installation of the synthetic turf surface continued last week with the addition of numbers, lines and hash marks, looking good! Crumb rubber and sand infill should be added this week.





All inlays complete
Second synthetic turf field base almost ready for surface!

Some other random photos...

Shop lifted installed, a top of the line Rotary Lift.
Thanks to the good folks from my hometown of Madison , Indiana!

Sodded quad area

Landscaping and sod coming out of pavilion into Red quad
One of these disks goes in the circle cutout in above photo...

Tuesday, May 8, 2012

May Aerials and Synthetic Turf Install

Moving right along and getting so very close!  We really couldn't ask for better weather as we wrap up construction at the Sports Park!
Enjoy the pics!








Sewing the seams together


As the synthetic turf is installed on one field, the base is being prepped for the second...





Lastly we were able to use some of our great new mowers on  the ball diamonds!