Here are some photos from last week's construction progress. They started the base for the synthetic fields and started installing the crushed brick to the warning tracks in baseball. Crews also continued to work on landscaping, roofing, steel erection, concrete flatwork, masonry, curbing, and paving. There were probably some other things that I forgot to mention. Lets keep this momentum going!
Synthetic field installation progress
Flat drainage pipe is laid on top of geotextile fabric and then covered with 6 inches of gravel
Crushed brick warning track installation
The crushed brick is placed over a fine crushed limestone base. When compacted the two materials will "lock" together and surface water will drain over the top.
Other random shots...
Steel beams for Sports Fields pavilion
Trees installed in Sports Fields parking lot
Standing at end of trail above Championship Fields, looking back at warmup area with grass coming up
Masonry seat wall in roundabout
No comments:
Post a Comment